Excavating for the new Addition




Looking up from the bottom of the hole

Just about done

Finished hole


Stocked piled gravel from hole to be used for backfilling walls


Starting to layout the new addition


Forming the footings



Ready for Concrete

Construction Begins!!!


Pumping Concrete for the footings






Completed Footings





Forming the "Step Footings"

Starting fo form the basement walls





Ready for concrete

Filling the walls with concrete






Pump truck set up on Broadway



Finished wall


Moving the forms for the next wall pour







Unloading structural steel

Ready for the next pour.


Pumping concrete

Water proofing attached to the exterior wall

Pumping Concrete in the north wall

Backfilling is started




Starting to form the elevator shaft


Backfilliing the narthex area

Foundation walls almost complete

Grading the Basement


Adding the final gravel to the narthex area

Grading the basement floor

Plumber starting the "rough in" in the basement bathrooms

Narthex almost ready for concrete

Vapor barrier is installed under concrete

Pouring the concrete floor in the Narthex area


Plumbing "rough in" complete for the basement bathrooms

Ready for concrete

Finished concrete slab in the Narthex

Power company getting ready to relocate power poles.